Over a period of 10 bending days, a total of 56 pipes were processed. Since the order covered several different sections of the route, completion took a longer period of time.

Among other things, this project also involved bending an S-bend with 8.1° per side, which impressively demonstrates the precision and flexibility of our technology.

The bending angles for this order ranged from 3.98° to 16.4°, ensuring that all pipes met the specified requirements of the route exactly.

Brief overview

  • 56 bend pipes
  • 3.98° minimum angle
  • 16.4° maximum angle
  • 10 deployment days